How to Plan Network Cabling for an Office Move

How to Plan Network Cabling for an Office Move

Network cabling is the part of an office move that cannot be finished on move weekend. Cable has to be pulled, terminated, tested, and labeled before desks and equipment arrive. Some of that work also depends on the landlord, the internet carrier, and the general contractor.

ACECOMM Inc is a low-voltage contractor in Las Vegas. The eight steps below follow the order the work usually happens in, and the plan can start as soon as you have a signed lease and a floor plan.

1. Check what is already in the new space


Most office suites come with cabling left by the last tenant, and some of it may be usable. Read the print on the cable jacket for the category. Check whether both ends are labeled, and ask the landlord for any drawings or test records. Unlabeled cable of unknown age should be tested before anyone relies on it.

A site walk with a network cabling contractor settles which runs can stay and which locations are missing. It also shows whether the old cable suits the ceiling. A ceiling space used for return air requires plenum-rated cable unless the cable is in metal raceway (NEC 300.22(C)).

2. Count the drops from the furniture plan


Mark every wired device on the furniture plan before you ask for a price. ANSI/TIA-568 calls for a minimum of two outlets at each work area. Desks are rarely forgotten. These locations often are:

  • Printers and copiers
  • Conference room tables and wall displays
  • Ceiling locations for wireless access points
  • Security cameras and door readers
  • Reception desks, break rooms, and time clocks

Add spare outlets where layouts change most, such as open areas and meeting rooms. A drop added during the main installation costs less than one added after the ceiling is closed and the furniture is in place.

3. Pick a cable category for the length of the lease


Category 6 supports gigabit speeds over the full 100-meter channel, and 10 gigabit only up to 55 meters. Category 6A carries 10 gigabit the full distance. Cat6A is worth pricing at least for wireless access point locations, where a common design practice is two Cat6A cables per access point.

The same cable also powers devices. Phones, access points, cameras, and door readers draw Power over Ethernet from the switch. A port supplies up to 15.4 watts under IEEE 802.3af, 30 watts under 802.3at, and as much as 90 watts under 802.3bt. Give your IT provider the device list so the switches are sized for it.

A run longer than 90 meters of installed cable cannot stay on copper, and links between floors or separate suites are usually better served by fiber. Fiber optic installation should be planned in the same drawing as the copper.

4. Place the network room first


The 90-meter limit on each installed run decides where the network room can go. A room near the center of the floor keeps every outlet in range. Confirm that the room has:

  • Dedicated power for the rack
  • Cooling or ventilation that runs after hours
  • A locking door
  • Wall or floor space for a rack and patch panels

In a multi-tenant building, ask where the carrier’s service enters the property. The cable from that point to your suite is often the tenant’s job to arrange.

5. Order internet service early


Internet service is often the item with the longest lead time. Ask the property manager which carriers already serve the building, then place the order as soon as the lease is signed. A new fiber circuit can take weeks, and longer if the carrier has to build into the property. Keep service at the old office active until the new circuit has been tested. If your phone numbers are moving to a new provider, ask about porting at the same time, because it has its own lead time.

6. Schedule the work around ceilings, furniture, and movers


The work follows a fixed order:

  1. Cable is pulled while ceilings and walls are open, or before furniture arrives in a finished space
  2. Jacks and patch panels are terminated
  3. Every run is tested and labeled
  4. Switches, access points, and phones are installed
  5. Staff and equipment move in

In a buildout, the cabling crew works to the general contractor’s schedule, so bring your low voltage contractor into the project meetings early. Systems furniture needs its own coordination, because cable is fed through the panels while the furniture is being installed.

7. Get test results and labels before move day


Ask for a test report on every cable and a floor plan that shows each outlet number. Labels on the wall plate and the patch panel should match that plan. With that record, your IT provider can connect each desk quickly and trace a dead port without opening the ceiling. Keep a copy with the lease file, since it is also useful for the next tenant improvement.

8. Close out the old office


Read the old lease for a cabling clause, since many leases require the tenant to remove what it installed. The National Electrical Code also requires the accessible portion of abandoned communications cable to be removed unless it is tagged for future use (NEC 800.25). Local code adoption varies, so confirm the requirement with your contractor. Return the carrier’s equipment, and cancel the old circuit only after the new office is running.

Put cameras and door access on the same drawing

Cameras, door readers, and intercoms use the same kind of cable and end in the same network room. If security camera installation is priced with the data cabling, the ceiling work happens once.

Access control systems need cable at each controlled door and power for the locks. Door locations should be on the plan before the walls are finished.

Frequently asked questions


1) How far ahead should we plan cabling for an office move?

Start when you have a signed lease and a floor plan. The internet order and the site walk can happen right away, and the cable has to be tested before furniture and equipment arrive.

2) Can we reuse the cabling the last tenant left behind?

Sometimes. Each run should be tested, and the category, labeling, and outlet locations need to match what your layout requires. Cable that fails a test or ends in the wrong place is replaced.

3) Do we still need cabling if the office will be mostly on Wi-Fi?

Yes. Every wireless access point is fed by cable from the network room, and printers, conference room equipment, cameras, and desktop computers still work best on a wired connection.

4) Do phones and computers need separate cabling?

Not separate types. VoIP phones run on the same data cabling as computers. Two outlets per desk leaves room for a phone, a computer, and a later change without a new cable pull.

5) Does the landlord need to approve the cabling plan?

Check the lease and ask the property manager. Buildings commonly ask to review the plan, require a certificate of insurance from the contractor, and limit work to set hours.

Conclusion


An office move has one fixed date, and the cabling has to be finished ahead of it. A floor plan and a drop count are enough to start.

ACECOMM Inc works with businesses across Las Vegas from its office on South Valley View Boulevard. Call 702.873.1007 or request a free consultation, and have your floor plan and move date ready.